Login
Apr. 29, 2024
Casing is a large diameter pipe that is assembled and inserted into a recently drilled section of a borehole. Similar to the bones of a spine protecting the spinal cord, casing is set inside the drilled borehole to protect and support the wellstream. The lower portion (and sometimes the entirety) is typically held in place with cement.[1] Deeper strings usually are not cemented all the way to the surface, so the weight of the pipe must be partially supported by a casing hanger in the wellhead.
For more information, please visit our website.
Casing that is cemented in place aids the drilling process in several ways:[2]
Optimum design of the casing program decreases the well construction costs, enhances the efficiency of operations and also diminishes the environmental impacts.[3]
Casing arranged on a rack at a drilling rig in preparation for installationA slightly different metal string, called production tubing, is often used without cement inside the final casing string of a well to contain production fluids and convey them to the surface from an underground reservoir.
Design
[
edit
]
In the planning stages of a well, a drilling engineer, usually with input from geologists and others, will pick strategic depths at which the hole will need to be cased in order for drilling to reach the desired total depth. This decision is often based on subsurface data such as formation pressures and strengths, well integrity,[4] and is balanced against the cost objectives and desired drilling strategy.[2]
With the casing set depths determined, hole sizes and casing sizes must follow. The hole drilled for each casing string must be large enough to accommodate the casing to be placed inside it, allowing room for cement between the outside of that casing and the hole. Also, subsequent bits that will continue drilling obviously must pass through existing casing strings. Thus, each casing string will have a subsequently smaller diameter. The inside diameter of the final casing string (or penultimate one in some instances of a liner completion) must accommodate the production tubing and associated hardware such as packers, gas lift mandrels and subsurface safety valves.
Casing design for each size of designed pipes is done by calculating the worst conditions that may be faced during drilling and over the producing life of the well. Mechanical properties such as longitudinal tensile strength, and burst and collapse resistance (calculated considering biaxial effects of axial and hoop stresses), must be sufficient at various depths. Pipe of differing strengths often comprises a long casing string, which typically will have the greatest axial tension and perhaps highest internal burst pressure differentials in the upper parts, and the greatest collapsing loads deeper in the well from external pressure vs lowered internal pressure.
Casing strings are supported by casing hangers that are set in the wellhead, which later will be topped with the Christmas tree. The lower members of the wellhead usually are installed on top of the first casing string after it has been cemented in place.
Intervals
[
edit
]
Typically, a well contains multiple intervals of casing successively placed within the previous casing run.[2] The following casing intervals are typically used in an oil or gas well:
The conductor casing serves as a support during drilling operations, to flowback returns during drilling and cementing of the surface casing, and to prevent collapse of the loose soil near the surface. It can normally vary from sizes such as 18" to 30".[5]
The purpose of surface casing is to isolate freshwater zones so that they are not contaminated during drilling and completion. Surface casing is the most strictly regulated due to these environmental concerns, which can include regulation of casing depth and cement quality. A typical size of surface casing is 13⅜ inches.[5]
Intermediate casing may be necessary on longer drilling intervals where necessary drilling mud weight to prevent blowouts may cause a hydrostatic pressure that can fracture shallower or deeper formations. Casing placement is selected so that the hydrostatic pressure of the drilling fluid remains at a pressure level that is between formation pore pressures and fracture pressures.[6][5]
In order to reduce cost, a liner may be used which extends just above the shoe (bottom) of the previous casing interval and hung off downhole rather than at the surface. It may typically be 7", although many liners match the diameter of the production tubing.[5]
Few wells actually produce through casing, since producing fluids can corrode steel or form deposits such as asphaltenes or paraffin waxes and the larger diameter can make flow unstable. Production tubing is therefore installed inside the last casing string and the tubing annulus is usually sealed at the bottom of the tubing by a packer. Tubing is easier to remove for maintenance, replacement, or for various types of workover operations. It is significantly lighter than casing and does not require a drilling rig to run in and out of hole; smaller "service rigs" are used for this purpose.
Cementing
[
edit
For more information, please visit Yulin Machinery.
]
Cementing is performed by circulating a cement slurry through the inside of the casing and out into the annulus through the casing shoe at the bottom of the casing string. In order to precisely place the cement slurry at a required interval on the outside of the casing, a plug is pumped with a displacement fluid behind the cement slurry column, which "bumps" in the casing shoe and prevents further flow of fluid through the shoe. This bump can be seen at surface as a pressure spike at the cement pump. To prevent the cement from flowing back into the inside of the casing, a float collar above the casing shoe acts as a check valve and prevents fluid from flowing up through the shoe from the annulus.
Casing Wear
[
edit
]
A prolonged, recurrent axial and rotational movement within casing would cause wear to the casing interior, with the probability of blowouts, production loss, and other hazardous and costly complications.
The following conditions contribute to casing wear:
The following are recommendations for preventative measures to minimize casing wear:
References
[
edit
]
In petroleum production, the casing hanger is that portion of a wellhead assembly which provides support for the casing string when it is lowered into the wellbore. It serves to ensure that the casing is properly located. When the casing string has been run into the wellbore it is hung off, or suspended, by a casing hanger, which rests on a landing shoulder inside the casing spool. Casing hangers must be designed to take the full weight of the casing, and provide a seal between the casing hanger and the spool.
Casing Hangers may also be suspended within the wellhead by means of radial distortion of the wellhead bore e.g. the "Pos-Grip" method.
This is installed to support the individual casing strings in the well. It is the landing base or the casing head. This is usually welded or screwed to the top of the surface casing string. The surface casing serves as a foundation pile for the well which transfers the hanging load to the earth. The casing head is prepared with a bowl into which the slips sit and chuck the casing in place. Most casing heads allow for the pressure readings to be taken on the annulus and provide the means to pump out or into if necessary. The top of the casing string and annulus is usually sealed.
The most common size of casing hanger is 13+3⁄8 in (340 mm) with over 155,000 such units installed worldwide in 2014 alone.
The contraction of the oilfield industry throughout 2015 meant that this figure was reduced somewhat to just under 120,000 units, of which 36,822 were "Pos-Grip" casing hangers.
Intermediate, or protective, casing may be one or more strings of casing. Protective casing is most frequently installed in a well because of the mud weight required to drill deeper in the well. Common sizes of intermediate strings range from 7 in (180 mm) to 10+3⁄4 in (270 mm) (or larger in deep wells). Each string is cemented in place. Obviously, if several strings of intermediate casing are required in a well, the diameter of the surface hole must be large enough to permit all of the necessary strings. Wells are planned from the bottom up. The purpose of the well determines the diameter of the bottom of the well. If the well is an exploratory wild cat offshore, the bottom of the well must be only large enough to accommodate a logging sonde. If the well is a very productive oil well, a 7 in (180 mm) production tubing might be installed in a larger diameter casing. Gas wells may only require a small 2+7⁄8 in (73 mm) tubing set in 4+3⁄4 in (120 mm) casing, so the hole might be relatively small. With rank wildcats in geological basins that have not been explored extensively, the first holes might be large enough to provide for a couple of contingency strings of casing.
See also
[
edit
]
Plastik Askı
Additional resources:Casing is a large diameter pipe that is assembled and inserted into a recently drilled section of a borehole. Similar to the bones of a spine protecting the spinal cord, casing is set inside the drilled borehole to protect and support the wellstream. The lower portion (and sometimes the entirety) is typically held in place with cement.[1] Deeper strings usually are not cemented all the way to the surface, so the weight of the pipe must be partially supported by a casing hangercasing hanger in the wellhead.
Casing that is cemented in place aids the drilling process in several ways:[2]
Optimum design of the casing program decreases the well construction costs, enhances the efficiency of operations and also diminishes the environmental impacts.[3]
Casing arranged on a rack at a drilling rig in preparation for installationA slightly different metal string, called production tubing, is often used without cement inside the final casing string of a well to contain production fluids and convey them to the surface from an underground reservoir.
Design
[
edit
]
In the planning stages of a well, a drilling engineer, usually with input from geologists and others, will pick strategic depths at which the hole will need to be cased in order for drilling to reach the desired total depth. This decision is often based on subsurface data such as formation pressures and strengths, well integrity,[4] and is balanced against the cost objectives and desired drilling strategy.[2]
With the casing set depths determined, hole sizes and casing sizes must follow. The hole drilled for each casing string must be large enough to accommodate the casing to be placed inside it, allowing room for cement between the outside of that casing and the hole. Also, subsequent bits that will continue drilling obviously must pass through existing casing strings. Thus, each casing string will have a subsequently smaller diameter. The inside diameter of the final casing string (or penultimate one in some instances of a liner completion) must accommodate the production tubing and associated hardware such as packers, gas lift mandrels and subsurface safety valves.
Casing design for each size of designed pipes is done by calculating the worst conditions that may be faced during drilling and over the producing life of the well. Mechanical properties such as longitudinal tensile strength, and burst and collapse resistance (calculated considering biaxial effects of axial and hoop stresses), must be sufficient at various depths. Pipe of differing strengths often comprises a long casing string, which typically will have the greatest axial tension and perhaps highest internal burst pressure differentials in the upper parts, and the greatest collapsing loads deeper in the well from external pressure vs lowered internal pressure.
Casing strings are supported by casing hangers that are set in the wellhead, which later will be topped with the Christmas tree. The lower members of the wellhead usually are installed on top of the first casing string after it has been cemented in place.
Intervals
[
edit
]
Typically, a well contains multiple intervals of casing successively placed within the previous casing run.[2] The following casing intervals are typically used in an oil or gas well:
The conductor casing serves as a support during drilling operations, to flowback returns during drilling and cementing of the surface casing, and to prevent collapse of the loose soil near the surface. It can normally vary from sizes such as 18" to 30".[5]
The purpose of surface casing is to isolate freshwater zones so that they are not contaminated during drilling and completion. Surface casing is the most strictly regulated due to these environmental concerns, which can include regulation of casing depth and cement quality. A typical size of surface casing is 13⅜ inches.[5]
Intermediate casing may be necessary on longer drilling intervals where necessary drilling mud weight to prevent blowouts may cause a hydrostatic pressure that can fracture shallower or deeper formations. Casing placement is selected so that the hydrostatic pressure of the drilling fluid remains at a pressure level that is between formation pore pressures and fracture pressures.[6][5]
In order to reduce cost, a liner may be used which extends just above the shoe (bottom) of the previous casing interval and hung off downhole rather than at the surface. It may typically be 7", although many liners match the diameter of the production tubing.[5]
Few wells actually produce through casing, since producing fluids can corrode steel or form deposits such as asphaltenes or paraffin waxes and the larger diameter can make flow unstable. Production tubing is therefore installed inside the last casing string and the tubing annulus is usually sealed at the bottom of the tubing by a packer. Tubing is easier to remove for maintenance, replacement, or for various types of workover operations. It is significantly lighter than casing and does not require a drilling rig to run in and out of hole; smaller "service rigs" are used for this purpose.
Cementing
[
edit
]
Cementing is performed by circulating a cement slurry through the inside of the casing and out into the annulus through the casing shoe at the bottom of the casing string. In order to precisely place the cement slurry at a required interval on the outside of the casing, a plug is pumped with a displacement fluid behind the cement slurry column, which "bumps" in the casing shoe and prevents further flow of fluid through the shoe. This bump can be seen at surface as a pressure spike at the cement pump. To prevent the cement from flowing back into the inside of the casing, a float collar above the casing shoe acts as a check valve and prevents fluid from flowing up through the shoe from the annulus.
Casing Wear
[
edit
]
A prolonged, recurrent axial and rotational movement within casing would cause wear to the casing interior, with the probability of blowouts, production loss, and other hazardous and costly complications.
The following conditions contribute to casing wear:
The following are recommendations for preventative measures to minimize casing wear:
References
[
edit
]
In petroleum production, the casing hanger is that portion of a wellhead assembly which provides support for the casing string when it is lowered into the wellbore. It serves to ensure that the casing is properly located. When the casing string has been run into the wellbore it is hung off, or suspended, by a casing hanger, which rests on a landing shoulder inside the casing spool. Casing hangers must be designed to take the full weight of the casing, and provide a seal between the casing hanger and the spool.
Casing Hangers may also be suspended within the wellhead by means of radial distortion of the wellhead bore e.g. the "Pos-Grip" method.
This is installed to support the individual casing strings in the well. It is the landing base or the casing head. This is usually welded or screwed to the top of the surface casing string. The surface casing serves as a foundation pile for the well which transfers the hanging load to the earth. The casing head is prepared with a bowl into which the slips sit and chuck the casing in place. Most casing heads allow for the pressure readings to be taken on the annulus and provide the means to pump out or into if necessary. The top of the casing string and annulus is usually sealed.
The most common size of casing hanger is 13+3⁄8 in (340 mm) with over 155,000 such units installed worldwide in 2014 alone.
The contraction of the oilfield industry throughout 2015 meant that this figure was reduced somewhat to just under 120,000 units, of which 36,822 were "Pos-Grip" casing hangers.
Intermediate, or protective, casing may be one or more strings of casing. Protective casing is most frequently installed in a well because of the mud weight required to drill deeper in the well. Common sizes of intermediate strings range from 7 in (180 mm) to 10+3⁄4 in (270 mm) (or larger in deep wells). Each string is cemented in place. Obviously, if several strings of intermediate casing are required in a well, the diameter of the surface hole must be large enough to permit all of the necessary strings. Wells are planned from the bottom up. The purpose of the well determines the diameter of the bottom of the well. If the well is an exploratory wild cat offshore, the bottom of the well must be only large enough to accommodate a logging sonde. If the well is a very productive oil well, a 7 in (180 mm) production tubing might be installed in a larger diameter casing. Gas wells may only require a small 2+7⁄8 in (73 mm) tubing set in 4+3⁄4 in (120 mm) casing, so the hole might be relatively small. With rank wildcats in geological basins that have not been explored extensively, the first holes might be large enough to provide for a couple of contingency strings of casing.
See also
[
edit
]
Plastik Askı
51 0 0
Join Us
Comments
All Comments ( 0 )